Okay, time to make it happen. By now you need to have both of your projects in mind. Please send me both of your preproposals if you haven't already. For your blog post, please detail your timeline for the completion of your projects. I need to know when you plan to complete your grant proposals, but also an estimated timeline for your project completion.
This is my timeline for the playground project.
Preliminary Design - May 1
Finalized Design - June 1
Request for Bids - June 8
Acceptance of Winning Bid - June 15
Removal of Old Equipment and Gravel - June 16 (performed by church volunteers)
Resurfacing (needs at least one week to cure) - July 3
Installation of New Equipment - July 17
Safety Testing - July 24
Open to Public - August 14
The timeline for the CPR Equipment project is somewhat different:
Research on costs - April 1
Meeting with church staff (Brian and Lisa) to finalize equipment decisions - April 17
Proposal letter to Mustard Seed Foundation - April 18
Proposal, with budget and timeline - April 24
Receipt of funds - Depends upon MSFDN
Equipment purchase - Depends upon MSFDN (as soon as funds received)